Month 6: Supply and Installation of Cables, Testing of all traffic signal equipment and Lanterns. Installation of Breaker for Power Supply, completion of Road Signages and Pavement Markings. Installation of Pavers along the new sidewalk and completion of concrete ramp with relocation of lamp post at UniMart side.